Development of project cost contingency estimation model using risk analysis and fuzzy expert system
Contractors traditionally estimate cost contingency based on subjective judgment, such as 5–10% from the cost estimated by considering past similar project. However, such method does not have a sound basis and is difficult to justify or defend. Therefore, more objective methods for estimating proj...
| Main Authors: | Idrus, Arazi, Nuruddin, F, Rohman, M.Arif |
|---|---|
| Format: | Article |
| Institution: | Universiti Teknologi Petronas |
| Record Id / ISBN-0: | utp-eprints.3281 / |
| Published: |
Elsevier
2010
|
| Subjects: | |
| Online Access: |
http://eprints.utp.edu.my/3281/1/ESWA4955.pdf http://eprints.utp.edu.my/3281/ |
| Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
| Summary: |
Contractors traditionally estimate cost contingency based on subjective judgment, such as 5–10% from
the cost estimated by considering past similar project. However, such method does not have a sound
basis and is difficult to justify or defend. Therefore, more objective methods for estimating project cost
contingency have been presented. However, most of the methods still rely on formal modeling techniques,
which is not easy to be applied in construction industry. This research proposes a method to estimate
cost contingency using a flexible and rational approach that could accommodate contractors’subjective judgment based on risk analysis and fuzzy expert system concept. In this research, the proposed method involved the development of cost contingency model for building and infrastructure projects in Malaysia. According to the validation result, it was found that the predictions given by the system were within 20% accuracy compared to actual cost contingencies. |
|---|